Three horizontal wells for a producing layer were drilled and their total length amounts to 995 meters (the first wellslot is 408 m, the second is 394 m, the third is 193 m). The actual bottoms of wells amounted to 2566 m, 2664 m, and 2610 m respectively.

The second multilateral well was drilled at a field in Western Siberia. In the second operating well, two lateral boreholes were drilled with a horizontal end to a producing layer with a total length of 1,144 meters (the first well – 679 m, the second – 465 m), the bottoms of wells were 2802 m and 2665 m, respectively.

After the development and flow back of wells, they were put into operation by the customer.